Streamlining the Consents Process for Ports and Harbours: A Practical Response to Offshore Wind Demands

The Growing Role of Ports in Offshore Wind

As the offshore wind sector continues to expand, particularly in the UK and Europe, ports and harbours are being redefined as critical enablers of this transition. No longer just gateways for trade, they are now central to the assembly, deployment, and maintenance of offshore wind farms, including the increasingly prominent floating offshore wind turbines. However, this transformation is not without its challenges. One of the most significant barriers to progress is the complexity of the consent process.

Understanding the Challenge: Fragmented Consenting Pathways

Port developments that support offshore wind infrastructure often require both marine and terrestrial consents. These are governed by different regulatory frameworks, involve separate authorities, and demand distinct technical assessments. For port and harbour authorities, this creates a fragmented and often frustrating experience. Projects can stall due to misaligned timelines, duplicated assessments, or unclear responsibilities between different stakeholders and regulators. The result is not just delay, but increased cost and uncertainty, particularly problematic in a sector where timing and coordination are critical.

Integration, Clarity, and Early Coordination

There is a market requirement for a more joined-up approach to consenting. This includes integrated Environmental Impact Assessments (EIAs) that cover both marine and terrestrial scopes, clearer guidance on aligning multiple regulatory pathways, and early stakeholder engagement to identify and address concerns before they escalate. Data-driven feasibility studies are also essential to inform site selection and risk mitigation, ensuring that projects are viable from the outset.

‘‘

Data should be used not just to meet regulatory requirements, but to inform decision-making and build confidence among all parties involved.

’’

The Role of Feasibility Studies in De-Risking Projects

Feasibility studies play a vital role in reducing consent risk. For large-scale offshore wind projects, early-stage analysis of navigational risk, vessel traffic, and spatial constraints helped inform site selection and reduce the risk of objections later in the process. These studies are not just technical exercises, they are strategic tools that help developers make informed decisions and avoid costly rework.

Emerging Best Practices for Streamlined Consents

From these and other projects, several best practices are emerging. Environmental and navigational assessments should be integrated from the outset, rather than treated as parallel or sequential tasks. Stakeholder engagement should begin early and be sustained throughout the project lifecycle. Co-ordination mechanisms, such as the coastal concordat should be discussed from the outset and made the most of. Data should be used not just to meet regulatory requirements, but to inform decision-making and build confidence among all parties involved.

In addition, monitoring solutions, such as those for invasive non-native species or marine ecology, can be embedded into routine port operations, reducing disruption and ensuring ongoing compliance.

Lessons from the Field: Insights from Recent Projects

Several recent projects offer valuable lessons on how to address these challenges.  In the Solent Gateway project, early navigation risk assessments and structured stakeholder consultation helped to surface and resolve potential conflicts before they could delay the project. Similarly, the Liverpool Cruise Terminal project required detailed assessments of plankton, benthic invertebrates, fish, marine mammals, and ornithology, particularly in relation to nearby European Marine Sites. By addressing these issues early and thoroughly, the project team was able to build a strong case for consent.

Meanwhile, the London Gateway Port Berths 5 & 6 development integrated HRA screening and Stage 2 assessments into early project planning, helping to streamline regulatory approvals.

Solent Gateway ships docked

Solent Gateway

London gateway 4th berth aerial view

London Gateway 4th Berth

Looking Ahead: Enabling the Offshore Wind Transition

As the offshore wind sector, particularly floating offshore wind, continues to grow, ports and harbours will play an increasingly strategic role. But to fulfil this role, they must be supported by a consenting process that is efficient, transparent, and fit for purpose.

By learning from recent projects and adopting a more integrated, data-informed approach, stakeholders can reduce delays, manage risk, and ensure that ports are ready to support the next generation of offshore wind power.

 

Contact us

Get in touch if you’ve got any questions or would like to receive more content like this

Related Articles

aus osw webinar mm

Supporting Offshore Wind Success – Explore Our New E-book

As the offshore wind industry evolves, APEM Group is here to help you navigate complexity with confidence. Our new e-book...

Read More
Signal crayfish

eDNA and the fight against invasive non-native species (INNS)

Invasive non-native species (INNS) are one of leading causes of biodiversity loss worldwide and there is a demand for more...

Read More
Underwater seagrass meadow, providing vital habitat for marine life and supporting coastal biodiversity.

Building a healthier future for marine ecosystems with Marine Net Gain

Marine Net Gain (MNG) is a concept aimed at improving marine environments post-development. With rising demand for sustainable infrastructure, and...

Read More